Temporary Sheet Piling Explained
Temporary sheet piling is one of the most widely used methods of temporary works in construction. From supporting deep excavations to forming dry working areas near water, it offers a fast, robust, and adaptable solution across a wide range of commercial and infrastructure projects. In this guide, we explain what temporary sheet piling is, when it should be used, and why it continues to be the preferred option for contractors and engineers working in challenging ground conditions.
What Is Temporary Sheet Piling?
Temporary sheet piling involves installing steel sheet piles to provide earth or water retention for a limited period during construction. The piles are typically extracted once their temporary purpose has been served, allowing the site to proceed to its next phase or return to its original condition.
Steel sheet piles interlock to form a continuous wall. They are installed using vibratory hammers, hydraulic press-in rigs, or excavator-mounted attachments, depending on access, ground conditions, and environmental constraints. Unlike permanent installations, temporary piles are usually selected with reuse in mind and may be driven and extracted multiple times across different projects.
Typical Uses of Temporary Sheet Piling on Site
Temporary sheet piling is used wherever a stable barrier is needed during an active phase of construction. Common applications include:
Excavation Support
When constructing deep foundations, basements, or utility trenches, the surrounding ground must be stabilised to prevent collapse or slippage. Temporary sheet piles form a retaining wall that resists soil pressure and allows safe excavation.
Cofferdams
For work near or within bodies of water, such as bridge piers, culverts, or marine structures, temporary cofferdams are created using sheet piles. These enclosures allow the interior to be dewatered so work can proceed in the dry.
Temporary Flood Protection
During site preparation or remedial works in flood-prone areas, temporary sheet piles can be used as emergency barriers or to divert water away from active work zones.
Utility Works and Infrastructure Installation
Sheet piles are used to stabilise trenches and shafts for pipe laying, culvert installation, and cable runs, especially where the ground is unstable or close to other assets.
Embankment Works and Road Construction
On highways, railways, or riverbanks, temporary piling may be used to retain soil during the construction of slopes, retaining walls, or bridge abutments.
Why Temporary Sheet Piling Is Chosen Over Other Methods
Temporary sheet piles offer several clear benefits over alternative methods like king post walls, timber shoring, or concrete supports:
Speed of Installation: Sheet piles can be driven rapidly using vibratory or press-in methods, reducing time on site.
Reusability: Temporary piles are often reused across multiple sites, reducing material costs and environmental impact.
Adaptability: They can be adjusted or reconfigured easily to suit changing site conditions.
Load Resistance: Sheet piles provide excellent lateral support against both soil and hydrostatic pressure.
Space Efficiency: Their thin profile means minimal footprint, ideal for constrained or urban sites.
Ease of Extraction: With proper planning and site conditions, piles can be removed without leaving a trace.
Installation Methods for Temporary Sheet Piling
The right installation method depends on site-specific factors such as ground type, noise restrictions, and available access. Common methods include:
Vibratory Installation
A vibratory hammer is used to drive sheet piles into the ground. It is efficient and widely used but can create vibration that may not be suitable near sensitive structures.
Silent Press-In (Hydraulic)
Where noise or vibration must be minimised (e.g. near railways or buildings), silent press-in rigs offer a controlled, low-impact solution. These machines use static force and clamp onto previously driven piles to install new ones.
Excavator-Mounted Attachments
For restricted access sites or smaller installations, side-grip hammers mounted to excavators (e.g. Movax systems) provide flexible, mobile piling solutions.
Each method can be adapted for temporary works, with extraction equipment used to recover the piles once no longer needed.
Temporary vs Permanent Sheet Piling: What’s the Difference?
While both use the same type of steel piles, the key differences are:
Design Life: Temporary piles are intended for short-term use, typically weeks or months, whereas permanent piles are designed for 50+ years.
Corrosion Protection: Temporary piles may not require full protective coatings if the exposure is brief. Permanent systems typically need corrosion allowances or coatings.
Installation Tolerance: Temporary works can allow for simpler driving methods and tolerances.
Extraction Planning: Temporary sheet piles must be installed with future removal in mind, including potential obstructions or embedment depths.
In some cases, temporary piles are left in place due to access limitations or changes in programme, but this should be addressed at design stage.
Considerations for Restricted Access Sites
Temporary sheet piling is particularly useful in constrained environments:
Urban construction sites with limited working room
Railway or infrastructure corridors requiring careful logistics
Basement excavations in existing buildings
Sites with overhead obstructions or limited headroom
In these cases, selecting the right piling method — such as silent pressing or compact rigs — and sequencing works with other trades is critical to success.
Planning and Design Best Practice
To ensure successful temporary piling, consider the following:
Engage a specialist piling contractor early to advise on method, plant, and logistics
Complete a detailed ground investigation to determine pile lengths and embedment
Factor in removal during the design to avoid clashes with permanent structures or obstructions
Coordinate with temporary works designers to integrate piling into the broader site safety and staging plan
Example: Retaining Wall for Excavation Works
On a typical construction site involving a new foundation or basement, temporary sheet piles may be driven to form a retaining wall at the excavation perimeter. This allows the interior ground to be safely excavated without soil collapse. Once the foundation, slab, or underground structure is constructed, the sheet piles are extracted and removed from site. This minimises long-term disruption and returns the site boundary to its final design.
Look for Buy-Back and Reuse Schemes
Many steel suppliers and piling contractors offer buy-back or reuse programmes for temporary sheet piles. These schemes can provide cost savings while promoting circular use of materials. By purchasing piles with a guaranteed return option or hiring from fleets that offer reuse, contractors can reduce their upfront investment and environmental impact. It’s worth discussing options for hire, buy-back, or recycled stock during early-stage procurement.
Final Thoughts
Temporary sheet piling is a practical, proven method for delivering safe working conditions during construction. Whether forming cofferdams, stabilising excavations, or supporting infrastructure, it plays a vital role in temporary works across the UK.
If you’re planning a project involving ground support or excavation near water, roads, or sensitive structures, speak to Steel Piling Solutions for advice on the best temporary piling method.
📞 01425 489600
📧 admin@steelpilingsolutions.com
Steel Piling Solutions – Delivering safe, effective temporary and permanent piling across the UK’s construction and infrastructure sectors.


